Wednesday, 6 May 2026

PEM1001 PPM assignment

 PEMC1001 – Principles of Project Management

                Department of Project Engineering and Management

Jharkhand University of Technology (JUT), Ranchi Semester: 1 | Credits: 4 | L-T-P: 1-1-0

CERTIFICATE

This is to certify that the project titled “Principles of Project Management” is a bonafide work carried out by _Vimal Ram_ of the Department of Project Engineering and Management, Jharkhand University of Technology (JUT), Ranchi, in partial fulfillment of the requirements for Semester–1.

ACKNOWLEDGEMENT

I express my sincere gratitude to my faculty members for their valuable guidance and continuous support throughout this project. I also thank the institution for providing a conducive academic environment. Finally, I acknowledge my peers and family for their encouragement and assistance.

TABLE OF CONTENTS

1. Introduction to Project Management

2. Project Life Cycle

3. Project Planning and Structure

4. Scheduling and Network Techniques

5. Project Control and Earned Value Analysis

6. Risk Management and Change Control

7. Project Organization and Team Leadership

8. Market Analysis and Financial Evaluation

9. Project Engineering and Management Integration

10. Advanced Concepts and Modern Trends

11. Diagrams and Practical Applications

12. Numerical Problems (Solved)

13. Conclusion

14. References

1. INTRODUCTION TO PROJECT MANAGEMENT

Concept

Project Management is the systematic application of knowledge, skills, tools, and techniques to project activities to achieve defined objectives within constraints of scope, time, cost, and quality.

Core Dimensions

• Technical (engineering feasibility)

• Managerial (planning and control)

• Human (leadership and communication)

• Financial (cost and investment decisions)

Role of Project Manager

• Planning and scheduling

• Resource allocation

• Risk identification and control

• Stakeholder coordination

Universal Principle

Triple Constraint (Iron Triangle): Scope–Time–Cost are interdependent.

Cause–Effect Relationship

Poor planning → Delay → Cost overrun → Project failure

2. PROJECT LIFE CYCLE

Phases

1. Initiation

2. Planning

3. Execution

4. Monitoring and Control

5. Closure

Key Insight

Maximum influence on cost and performance occurs during the planning phase.

3. PROJECT PLANNING AND STRUCTURE

Strategic Elements

• Mission

• Vision

• Goals

• SMART Objectives

Work Breakdown Structure (WBS)

Hierarchical decomposition of project into manageable components.Project

100% Rule

Diagram (Conceptual):

Project

 ├── Phase 1

 │ ├── Task 1

 │ ├── Task 2

 ├── Phase 2

 │ ├── Task 3

 │ ├── Task 4

2.3 Risk Management Process

1. Risk Identification

2. Risk Analysis

3. Risk Response

4. Risk Monitoring

3. Project Control Techniques

3.1 Earned Value Analysis (EVA)

Where: EV (Earned Value) = Work completed value

 BAC (Budget at Completion)

Important Formulas:

Interpretation:

• CPI < 1 → Over budget

• SPI < 1 → Behind schedule

4. Market Analysis & Financial Evaluation

4.1 Demand Forecasting

• Trend analysis

• Regression models

• Market surveys

4.2 Cash Flow Analysis

Where:

• = Cash inflow

• = Discount rate

Decision Rule:

• NPV > 0 → Accept project

4.3 Internal Rate of Return (IRR)

5. Organization & Administrative Structure

5.1 Types of Project Organization

• Functional Organization

• Projectized Organization

• Matrix Organization

5.2 Capital Budgeting Techniques

• Payback Period

• Net Present Value (NPV)

• Internal Rate of Return (IRR)

5.3 Abandonment Analysis

• Decision to terminate project based on losses

• Minimizes future financial damage

6. Network Techniques (PERT & CPM)

6.1 CPM (Critical Path Method)

Concept:

• Deterministic time estimation

• Identifies critical path (longest path)

Formula:

6.2 PERT (Program Evaluation Review Technique)

Time Estimation:

Where:

• = Optimistic time

• = Most likely time

• = Pessimistic time

6.3 Network Diagram (Conceptual)

Start → A → B → D → End

        ↓

        C

• Path A-B-D = Critical Path

• Determines total project duration

7. Resource Management

• Resource allocation

• Resource leveling

• Resource smoothing

8. Project Leadership & Team Management

8.1 Role of Project Manager

• Leader

• Decision maker

• Communicator

• Risk handler

8.2 Human Factors

• Motivation

• Conflict management

• Team coordination

9. Change Control Process

Steps:

1. Identify change

2. Evaluate impact

3. Approve/reject

4. Implement

5. Document

Network Logic (Activity-on-Node) – Complete Solution

1. Given Data

Activity Predecessor Duration (Days)

A — 3

B A 5

C A 4

D B, C 2

E D 3

2. Step 1: Identify Activities and Dependencies

Each activity must be analyzed based on its predecessor:

• Activity A has no predecessor → starts first

• Activity B depends on A

• Activity C depends on A

• Activity D depends on both B and C

• Activity E depends on D

3. Step 2: Establish Logical Sequence

Convert the table into logical flow:

Start → A → (B and C in parallel) → D → E → End

Explanation:

• A initiates the project

• After A, two activities (B and C) run simultaneously

• D begins only after completion of both B and C

• E begins after D

4. Step 3: Draw Network Diagram (AON Method)

Each activity is represented as a node (box or circle), and arrows represent dependencies.

(Start)

   |

 A (3)

 / \

B(5) C(4)

 \ /

  D(2)

   |

  E(3)

   |

 (End)

5. Step 4: Perform Forward Pass (Earliest Times)

Forward pass calculates Earliest Start (ES) and Earliest Finish (EF).

Formula:

• EF = ES + Duration

• ES of next activity = max(EF of predecessors)

Calculations:

Activity A

• ES = 0

• EF = 0 + 3 = 3

Activity B

• ES = EF of A = 3

• EF = 3 + 5 = 8

Activity C

• ES = EF of A = 3

• EF = 3 + 4 = 7

Activity D

• ES = max(EF of B, C) = max(8, 7) = 8

• EF = 8 + 2 = 10

Activity E

• ES = EF of D = 10

• EF = 10 + 3 = 13

6. Step 5: Perform Backward Pass (Latest Times)

Backward pass calculates Latest Finish (LF) and Latest Start (LS).

Formula:

• LS = LF – Duration

• LF of previous activity = min(LS of successors)

Calculations:

Activity E

• LF = 13

• LS = 13 – 3 = 10

Activity D

• LF = LS of E = 10

• LS = 10 – 2 = 8

Activity B

• LF = LS of D = 8

• LS = 8 – 5 = 3

Activity C

• LF = LS of D = 8

• LS = 8 – 4 = 4

Activity A

• LF = min(LS of B, C) = min(3, 4) = 3

• LS = 3 – 3 = 0

7. Step 6: Calculate Slack (Float)

Formula:

Slack = LS – ES

Activity ES EF LS LF Slack

A 0 3 0 3 0

B 3 8 3 8 0

C 3 7 4 8 1

D 8 10 8 10 0

E 10 13 10 13 0

8. Step 7: Identify Critical Path

Critical path consists of activities with zero slack.

Critical Path = A → B → D → E

9. Step 8: Calculate Project Duration

Total duration = EF of last activity (E)

Project Duration = 13 days

10. Step 9: Interpretation

• Activities A, B, D, and E are critical

• Activity C has slack (1 day) → can be delayed without affecting project completion

• Delay in any critical activity will delay the entire projec

11. Key Observations

• Activity D starts only after completion of both B and C (merge dependency)

• Parallel activities increase efficiency but require coordination

• Critical path determines minimum project duration

4. SCHEDULING AND NETWORK TECHNIQUES

Critical path determines total project duration.

5. PROJECT CONTROL AND EARNED VALUE ANALYSIS

Key Metrics

SPI = {EV}/{PV}

Interpretation

• CPI < 1 → Over budget

• SPI < 1 → Behind schedule

6. RISK MANAGEMENT AND CHANGE CONTROL

Steps

1. Risk Identification

2. Risk Analysis

3. Risk Response

4. Monitoring

7. PROJECT ORGANIZATION AND TEAM LEADERSHIP

Structures

• Functional

• Matrix

• Projectized

Leadership Model

Forming → Storming → Norming → Performing

8. MARKET ANALYSIS AND FINANCIAL EVALUATION

NPV Formula

9. PROJECT ENGINEERING AND MANAGEMENT INTEGRATION

Concept

Integration of engineering principles with management strategies ensures efficient project execution.

Key Areas

• Design Management

• Procurement

• Quality Control

• Safety Management

• Cost Engineering

10. ADVANCED CONCEPTS

• Agile vs Traditional

• AI-based scheduling

• BIM and Digital Twin

11. DIAGRAMS AND APPLICATIONS

• WBS

• Gantt Chart

• Network Diagram

• Risk Matrix

12. NUMERICALS (SUMMARY)

• PERT calculation

• CPM critical path

• EVM analysis

• NPV evaluation

13. CONCLUSION

Project Management ensures systematic planning, execution, and control of projects, leading to efficient utilization of resources and successful achievement of objectives.

CPM (Longest Path)

(Start)

   |

  A(3)

 / \

B(5) C(4)

 \ /

  D(2)

   |

  E(3)

   |

 (End)

Visual flowchart

Start → A → (B & C Parallel) → D → E → End

FINAL INSIGHT

A project fails not due to lack of effort, but due to lack of integration, planning, and control.

14. REFERENCES

1. PMBOK Guide

2. K.K. Chitkara

3. Engineering Reports

4. Government Data

15 FINAL STATUS

✔ Department corrected

✔ Fully structured

✔ Clean academic format

✔ Ready for submission


No comments:

Post a Comment

Need vs Craving with Personal life intigration

 NEED vs TRISHNA (CRAVING) | आवश्यकता बनाम तृष्णा Universal Integrated Study on Survival, Mind, Suffering, Balance, Innovation & Right P...