๐ ULTIMATE IE & OR REVISION (SMART + MEMORY MODE)
๐ฅ 1. PERT & CPM (Most Scoring Area)
๐ Core Logic (Remember This Chain)
- Activity time → Beta distribution
- Project time → Normal distribution (via CLT)
๐ Central idea: explains why total duration becomes normal.
๐ Key Formula Block
Use this whenever solving numericals:
- Variance:
\sigma^2 = \left(\frac{t_p - t_o}{6}\right)^2
๐ฏ Exam Traps
- Critical path = Longest time path (not shortest)
- Slack = 0 → Critical
- Crashing:
- Single CP → crash that path
- Multiple CP → crash all paths simultaneously
⚡ 2. Linear Programming (LPP)
๐ Golden Rules
- Solution lies at corner points
- Alternate optimum → 0 in reduced cost row
- Unbounded → No upper bound
๐ Duality Shortcut
- Max ↔ Min
- ≤ ↔ ≥
- Coefficients transpose
๐ 3. Queuing Theory (Formula Heavy)
๐ Core Relations
๐ฏ M/M/1 Quick Memory Table
| Concept | Formula |
|---|---|
| Utilization | ฯ = ฮป/ฮผ |
| Queue length | |
| Waiting time |
⚠️ Shortcut Insight
- If ฮป ≈ ฮผ → System unstable
- Always check: ฯ < 1
๐ฆ 4. Inventory (High Probability Questions)
๐ EOQ Core Formula
๐ฏ Key Concepts
- EOQ ignores shortages
- JIT → Batch size = 1
- MRP → derived from MPS
๐ญ 5. Production Systems (Theory = Direct Marks)
๐ Memory Table
| Type | Key Feature |
|---|---|
| Job Shop | High variety |
| Mass Production | High volume |
| Product Layout | Line balancing |
| Fixed Layout | Aircraft |
๐ 6. Forecasting
๐ Core Formula
๐ฏ Insight
- High ฮฑ → fast reaction
- Low ฮฑ → smooth/stable
๐ 7. Quality Control
๐ Important Charts
| Chart | Use |
|---|---|
| p-chart | Defective % |
| c-chart | Defects count |
๐ Control Limit Formula
UCL = \bar{p} + 3\sqrt{\frac{\bar{p}(1-\bar{p})}{n}}
๐ง 8. Reliability
๐ Key Logic
- Series → multiply
- Parallel → use complement
๐ Maintainability Formula
๐ฐ 9. Engineering Economy
๐ Must-Remember
- Straight line → constant depreciation
- SYD → decreasing depreciation
๐ Capital Recovery
CR = P(A/P,i,n)
๐ง 10. Learning Curve
๐ Core Model
๐ฏ Shortcut
- 80% curve → time reduces to 80% on doubling
⚡ 11. Super Fast Revision (30 เคธेเคंเคก เคฎें เคชूเคฐा OR)
๐ PERT → Beta → Normal
๐ CPM → Longest path
๐ LPP → Corner points
๐ Queue → ฯ < 1
๐ EOQ → Balance cost
๐ JIT → 1 unit
๐ Quality → 3ฯ limits
๐ Reliability → Series ×, Parallel complement
๐ Forecast → ฮฑ decides speed
๐ฏ FINAL EXAM STRATEGY (VERY IMPORTANT)
Since you’re preparing seriously (UPSC + M.Tech mindset):
✅ Do This:
- Revise this sheet 3 times
- Solve PYQs immediately after each topic
- Focus on:
- PERT/CPM numericals
- LPP graphical/simplex
- Queue formulas
❌ Avoid:
- Over-reading theory
- Memorizing without solving



No comments: